September 12, 2002
Honorable
Carol J. Carmody, Chairman
Board
of Inquiry
National
Transportation Safety Board
490
L’Enfant Plaza East, S.W.
Washington,
DC 20594
Re: Proposed
Findings, Proposed Probable Cause, and Proposed
Safety
Recommendations in the matter of the Derailment of
Canadian
Pacific Railway, Freight Train 292-16, Near Minot,
North
Dakota, on January 18, 2002
Dear
Madam Chairman:
The
Brotherhood of Maintenance of Way Employes (BMWE) has been granted party status
by the Board in the above investigation.
BMWE participated in the NTSB public hearing held July 15-16, 2002 in
Washington, D.C., and hereby submits these Proposed Findings, Proposed Probable
Cause, and Proposed Safety Recommendations to the Board for consideration.
Proposed Findings
At
approximately 1:19 a.m., CST, January 18, 2002, Canadian Pacific Railway
(CPR)Freight Train 292-16 with two locomotives and 112 cars derailed 31 cars
near Minot, North Dakota. Seven tank
cars carrying anhydrous ammonia were breached, and a vapor plume covered the
derailment site and community. More
than 210,000 gallons of anhydrous ammonia was released, resulting in a fatal
injury to one local resident and the rescue of approximately 60-65 residents
from the neighborhood. More that 300
people were injured and approximately 15,000 people were affected.
The
operating crew of Freight Train 292-16 reported that they felt a rough spot
while traveling eastbound at approximately 40 MPH on single main track near
milepost (MP) 471.65 on CPR’s Portal Subdivision of the St. Paul Service
Area. The point of derailment was west
of the City of Minot, N.D., within the limits of Ward County near MP 471.65.
Honorable Carol J. Carmody - 2 - September 12, 2002
The
main track is owned, inspected, maintained and operated by CPR. There is a substantial question as to
whether the number of maintenance forces assigned is sufficient for the
territory. Track foreman Schoenberg has
just two workers on his section crew.
They must inspect and maintain a 150-mile territory and in addition, are
not infrequently assigned to assist crews in adjacent districts (NTSB
Transcript at pp. 58-62). Track
supervisor Kroll, with only 16 track maintenance workers is responsible for 287
miles of branch and main line track, including classification yards and a
number of industry tracks (NTSB Transcript at p. 98). There are some 170 turn-outs and other switches in the territory
(NTSB Transcript at p. 99).
Post-accident actions validate the lack of adequate staffing. Following this derailment, approximately 60
track workers were added for a period of 8 weeks in order to effectuate the
large number of repair orders specially issued by FRA. Most of these workers were of furlough at the
time the derailment occurred (NTSB Transcript at pp. 101, 199, and 200.).
The
Portal Subdivision main track has a maximum allowable operating speed of 49 MPH
for freight trains, designating it as Federal Railroad Administration (FRA)
Class 4 track. In the area of the
derailment, CPR designated the maximum allowable speed at 40 MPH. There have been substantial increases in
the tonnage hauled over this track, with predictable added stresses, but no
increases in track maintenance forces (NTSB Transcript at p. 62 and 99). As a
result of the derailment, approximately 475 linear feet on main track was
destroyed. Thirteen (13) track panels
were installed to restore operations.
The
post accident inspection disclosed that the point of derailment occurred on
tangent track with 100 RE pound continuous welded rail (CWR). The rail through the derailment area was
restressed in 1998 with new anchors applied.
The track structure also consisted of wooden crossties (approximately 22
per 39' rail length) and double
shoulder tie plates with 2-3 cut spikes per plate. The track segment was supported with trap rock ballast with an
approximate depth of 6-8 inches under the crossties. Shoulder ballast was determined to be approximately 12 inches,
and the crosstie cribs were full of ballast.
The rail was box anchored at every other tie with Improved Fair
anchors. The Track Group investigation
did not observe a continuous or fully boxed anchoring pattern (every crosstie
box anchored) in the area of the derailment.
Recovered
from the derailment site was a piece of track component located between two
derailed cars (lumber car CP 319013 and tank car NATX 35798). The track component represented the west
half of a rail joint in the north rail.
The partial rail joint consisted of two bolts through rail joint bars
affixed to 100 RE pound rail. The rail
in the joint bars exhibited some rail breakage. The second half (east half) of the same rail joint was located
within the proximity of where the first half of the joint bars and rail pieces
were located. Both of the joint bars
were broken at the center portion of each bar and both joint bars appeared to
contain fatigue fractures. It was determined that this rail joint was the east
end of a plug section of rail cut in on the north rail in May 2000. Each of the rail ends that comprised the
east joint of the plug section also exhibited measurable rail end batter.
Honorable Carol J. Carmody - 3 - September 12, 2002
With
regard to the subsequent breach of seven tank cars carrying anhydrous ammonia,
it appears that the magnitude of the release, approximately 210,000 gallons of
anhydrous ammonia, may be in part attributable to the occurrence of “brittle
fracture” defects within the derailed tank cars themselves. This phenomenon apparently manifests in tank
cars manufactured with coarse-grain carbon steel alloys. These course-grain, non-normalized steel
tank cars are susceptible to “brittle fracture” defects, i.e., cracks or
fractures which develop over time in the tank car shell to which relatively
little energy need be applied to the crack or fracture area to progress a
failure and possible catastrophic loss of load. Cold weather operations also appear to increase the likelihood
of the occurrence of brittle fracture tank car defects.
Proposed Probable Cause
BMWE’s
review of available evidence and testimony of the parties leads us to conclude
that the probable cause of the CPR derailment on January 18, 2002 at Milepost
471.65, west of Minot, N.D. was joint bar failure at the east end of a rail
plug on the north rail. BMWE
concludes that the joint bars likely developed internal fatigue fractures
between the center bolt holes, and these fatigue fractures, not detectable with
the naked eye, led to a complete failure of the joint bars thus allowing the
rail ends to “pull apart,” causing a track defect which lead to the
derailment. We also conclude that the
probable cause of the joint bar failure was ultimately an insufficient
anchoring pattern which caused the joint bars, joint bolts, and rail ends to be
subjected to extreme forces caused by insufficiently restrained contraction of
the rail ends during cold weather months.
The investigation record reflects the ambient temperature at the time of
the derailment was approximately -5 degrees Fahrenheit.
It
is not entirely clear to BMWE whether the rail end fractures which occurred
within the joint resulted from the forces exerted on the bolt holes and rail
ends due to the insufficiently restrained longitudinal expansion and
contraction of the rail within the joint, or whether the rail end fractures
occurred as a result of the forces exerted on the rail end joint by the
derailment itself. Regardless, the
underlying proposed probable cause was the absence of “full-boxed” rail anchors approximately 200' each side of
the failed rail joint. A “full box”
anchoring pattern at rail joints and other locations susceptible to the
longitudinal forces of CWR is a well established and generally accepted engineering norm within the industry. The failure of CPR to require a full-box
anchoring pattern every tie 190-200' each side of the joint is the probable
cause for the rail joint failure, pull-apart,
and subsequent derailment.
Honorable Carol J. Carmody - 4 - September 12, 2002
Proposed Safety Recommendations
Proposed Recommendations to Canadian Pacific Railway:
1. Follow
CPR’s requirements for rail anchoring found in SPC 19, Rail Anchors, in
its entirety. Specifically, assure
compliance with Section 2.0(f) of SPC 19 which states, “For those joints created
in CWR through the process of cutting in rails, box anchor every tie for the
first 195 feet on either end of the strings that butt up to the newly installed
rail.”
2. Submit
all SPC’s relative to CWR installation, renewal, repair, and maintenance in
filing CPR’s CWR Program with FRA.
3. Require
full box anchoring pattern 195'-200' each side of every rail joint in CWR.
4. Increase quantity and quality of training
programs for Track Inspectors and other persons qualified under 49 CFR 213.7
relative to the installation, renewal,
repair, and maintenance of CWR.
5.Develop a user-friendly “field manual” for
CWR installation, renewal, repair and maintenance where all CWR related
standards and instructions can be readily accessed in one publication by
persons qualified under 49 CFR Part 213.7
6. Institute
and maintain a joint bar inspection and maintenance program, including the use
of new technologies to inspect joint bars for internal defects.
7.Accelerate replacement of 100 RE pound rail
on mainline track to a heavier rail section
on the Portal Subdivision.
8.Increase and maintain the number of track
maintenance forces sufficient to facilitate pro-active track inspection and
maintenance protocols and procedures.
9.Adopt a more comprehensive welding and joint
elimination program, and comply with CPR’s own SPC’s regarding welding of rail
plug joints within specified parameters.
Honorable Carol J. Carmody - 5 - September 12, 2002
Proposed Recommendations to the Federal Railroad
Administration
1.Require,
by regulation, mandatory full box
anchoring pattern 200' each side of every rail joint in CWR.
2.Require
all railroads to submit full and comprehensive plans for every aspect of CWR
installation, maintenance, repair, and renewal as part of their filing of a CWR
Program to FRA.
3.Establish
a mandatory list of items and specifications which must be included in each
railroads’ filing of a CWR Program.
4.Require
each CWR Program to include provisions for joint bar maintenance and
inspection.
5.Develop
regulatory guidelines for rail wear.
6.